Roadworks – Woodcote Estate area

We have received the following message from SGN –

In collaboration with Surrey County Council, 360 Group of Companies will be carrying out a project on behalf of SGN in the Cedar Hill area of Epsom. This work will replace existing metal pipes with plastic PE pipes to ensure that the local area continues to receive a safe and reliable gas supply for many years to come.

The work started on Tuesday 6 April and will continue until Monday 29 November.

The list of roads and the dates when the work will be completed is shown below.

Most of the work we are carrying out will require local transport to ‘Give and Take’ to safely pass our work area, However, in October and November, we will be working in Woodcote Green Road.  To ensure the safety of everyone around the site we will need to install temporary three-way lights between 04/10/2021 until 18/10/2021 and then again between 01/11/2021 until 15/11/2021. Further information about the temporary traffic lights will be provided nearer the start time of this work.

Please feel free to share this information with anyone you feel may benefit.

If you have any enquiries about this project, please contact our Customer Service team on freephone 0800 912 1700 or email customer@sgn.co.uk quoting reference SOE3363

Sunny Bank06/04/202124/05/2021
Barons Hurst03/05/202121/06/2021
Woodcote Hurst24/05/202105/07/2021
Hambledon Vale14/06/202112/07/2021
Hambledon Hill28/06/202102/08/2021
Warren Hill19/07/202123/08/2021
Pine Hill26/07/202109/08/2021
Oak Hill02/08/202106/09/2021
Cedar Hill23/08/202127/09/2021
Chantry hurst23/08/202106/09/2021
Woodcote Hurst06/09/202118/10/2021
Axwood13/09/202104/10/2021
Woodcote Green Road04/10/202118/10/2021
Digdens Rise18/10/202115/11/2021
Woodcote Green Road01/11/202115/11/2021
Sunny Bank08/11/202129/11/2021
Woodcote Green Road15/11/202129/11/2021
This entry was posted in Uncategorized. Bookmark the permalink.